DE19501323A1 - Process for drying solid insulation of electrical equipment transformer - Google Patents
Process for drying solid insulation of electrical equipment transformerInfo
- Publication number
- DE19501323A1 DE19501323A1 DE1995101323 DE19501323A DE19501323A1 DE 19501323 A1 DE19501323 A1 DE 19501323A1 DE 1995101323 DE1995101323 DE 1995101323 DE 19501323 A DE19501323 A DE 19501323A DE 19501323 A1 DE19501323 A1 DE 19501323A1
- Authority
- DE
- Germany
- Prior art keywords
- temperature
- windings
- oil
- transformer
- heating current
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- H—ELECTRICITY
- H01—ELECTRIC ELEMENTS
- H01F—MAGNETS; INDUCTANCES; TRANSFORMERS; SELECTION OF MATERIALS FOR THEIR MAGNETIC PROPERTIES
- H01F27/00—Details of transformers or inductances, in general
- H01F27/08—Cooling; Ventilating
- H01F27/10—Liquid cooling
- H01F27/12—Oil cooling
- H01F27/14—Expansion chambers; Oil conservators; Gas cushions; Arrangements for purifying, drying, or filling
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Drying Of Solid Materials (AREA)
- Insulating Of Coils (AREA)
- Housings And Mounting Of Transformers (AREA)
Abstract
Description
Bei der Erfindung wird ausgegangen von einem Verfahren zur Trocknung der Feststoffisolationen eines in einer elektrischen Anlage angeordneten Transformators nach dem Oberbegriff von Patentanspruch 1.The invention is based on a method for Drying the solid insulation one in an electrical System arranged transformer according to the preamble of Claim 1.
Ein derartiges Trocknungsverfahren wird bevorzugt bei Leistungstransformatoren angewendet, welche fest in eine elektrische Anlage, etwa ein Schaltfeld, eingebaut sind. Das Öl des zu trocknenden Leistungstransformators wird durch die Wand des Transformatorgehäuses nach außen geführt und dort in einer Ölaufbereitungsanlage erwärmt. Das erwärmte Öl wird ins Trans formatorgehäuse zurückgebracht und wälzt dabei das im Gehäuse befindliche Öl um. Alternativ kann das Öl aber auch ins Gehäuse eingesprüht werden. Das ins Gehäuse gebrachte, aufgeheizte Öl kommt in Kontakt mit den Feststoffisolationen des Transforma tors, erwärmt diese und trocknet sie durch Aufnahme von in den Isolationen vorhandenem Wasser. Das wasserhaltige Öl wird zur Aufbereitungsanlage geführt und in dieser Anlage entgast und entwässert. Aufgeheiztes, entgastes und entwässertes Öl wird sukzessive ins Transformatorgehäuse geführt und dient dort der weiteren Aufheizung und Trocknung der Feststoffisolationen. Such a drying process is preferred for Power transformers applied, which are fixed in a electrical system, such as a control panel, are installed. The oil of the power transformer to be dried is through the wall out of the transformer housing and there in one Oil treatment plant warmed up. The warmed oil is transferred to the trans brought back the formator housing and thereby rolls it in the housing located oil around. Alternatively, the oil can also enter the housing be sprayed. The heated oil brought into the housing comes into contact with the solid insulation of the Transforma tors, heats them and dries them by absorbing them into the Isolation of existing water. The water-containing oil becomes Processing plant led and degassed in this plant and drained. Heated, degassed and dewatered oil successively guided into the transformer housing and is used there further heating and drying of the solid insulation.
Zugleich wird das Öl des Transformators durch Entgasen und Ent wässern in der Aufbereitungsanlage parallel dazu aufbereitet.At the same time, the transformer oil is degassed and degassed water processed in parallel in the treatment plant.
Nach einer ersten Vortrocknungsphase, in der das Öl auf eine obere Öltemperatur von typischerweise 70 bis 80°C aufgeheizt ist, wird das Öl aus dem Transformatorgehäuse entfernt und das Gehäuse evakuiert. Es treten dann in besonders starkem Masse unerwünschte Gase und Dämpfe, wie insbesondere Wasserdampf, aus den Feststoffisolationen aus. Da sich hierbei die Feststoff isolationen rasch abkühlen wird der Transformator nach dieser Trocknungsphase erneut mit Öl aufgeheizt, vorgetrocknet und nach Ablassen des Öls erneut im Vakuum getrocknet.After an initial pre-drying phase, in which the oil upper oil temperature of typically 70 to 80 ° C heated the oil is removed from the transformer housing and that Evacuated housing. It then occurs to a particularly large extent unwanted gases and vapors, especially water vapor the solid insulation. Because this is the solid the transformer will cool down quickly after this Drying phase heated up again with oil, pre-dried and after draining the oil again dried in a vacuum.
Dieses Verfahren benötigt relativ lange Prozeßzeiten, da die zuvor beschriebenen Vortrocknungs- und Trocknungsphasen mehr mals durchlaufen werden müssen, da das von außen zugeführte Öl die Feststoffisolationen nur langsam erwärmt, und da lediglich Trocknungstemperaturen von typischerweise 70 bis 80°C erreicht werden. Zudem erwärmen sich die Feststoffisolationen ungleich mäßig. Ferner sinkt nach Ablassen des Öls und Evakuierung die Temperatur der Feststoffisolationen infolge Wasserverdampfung und Wärmeabstrahlung rasch ab, so daß der Grad der Trocknung gering ist und typischerweise mehr als 2% Wasser in den Isolationen verbleiben.This process requires relatively long process times because the predrying and drying phases previously described more times must be run through, since the oil supplied from the outside the solid insulation only warmed up slowly, and only because Drying temperatures of typically 70 to 80 ° C reached will. The solid insulation also heats up unevenly moderate. Furthermore, after the oil has been drained and evacuated, the pressure drops Solid insulation temperature due to water evaporation and heat radiation rapidly decrease, so that the degree of drying is low and typically more than 2% water in the Insulations remain.
Ein Verfahren zur Trocknung von ölgefüllten Verteiltransforma toren ist in EP 0 543 181 A1 beschrieben. Bei diesem Verfahren werden die Unterspannungswicklungen der zu trocknenden Transformatoren kurzgeschlossen. Die Transformatoren werden sodann in einen evakuierbaren Behälter gebracht, in dem die Ober- und Unterspannungswicklungen der Transformatoren mittels eines den Oberspannungswicklungen zugeführten niederfrequenten Heizstroms aufgeheizt werden. Durch Evakuierung des Behälters werden beim Aufheizen aus den Feststoffisolationen der Trans formatoren tretendes Gas und Wasser aus dem Behälter inneren entfernt und so ein hoher Trocknungsgrad der Feststoffisolatio nen erreicht. Dieses Verfahren benötigt einen evakuierbaren Behälter zur Aufnahme der zu trocknenden Transformatoren. Ein Einsatz dieses Verfahrens in einer elektrischen Anlage mit stationären Transformatoren ist daher nicht vorgesehen.A process for drying oil-filled distribution transformers gates is described in EP 0 543 181 A1. With this procedure the undervoltage windings are the ones to be dried Transformers short-circuited. The transformers are then placed in an evacuable container in which the Over and under voltage windings of the transformers by means of one of the low-frequency windings supplied to the high-voltage windings Heating current are heated. By evacuating the container when heating from the solid insulation, the Trans Formators escaping gas and water from the inner container removed and so a high degree of drying of the solid insulation achieved. This procedure requires an evacuable one Container to hold the transformers to be dried. On Use of this method in an electrical system stationary transformers are therefore not provided.
Der Erfindung, wie sie in Patentanspruch 1 angegeben ist, liegt die Aufgabe zugrunde, ein Verfahren zur Trocknung der Fest stoffisolationen eines ölgefüllten und in eine elektrische Anlage fest eingebauten Transformators zu schaffen, welches eine rasche und intensive Entwässerung und Entgasung seiner Feststoffisolationen vor Ort in der Anlage ermöglicht.The invention as set out in claim 1 lies the task is based on a method of drying the solid fabric insulation of an oil-filled and in an electrical To create plant built-in transformer, which rapid and intensive drainage and degassing of its Solid insulation possible on site in the plant.
Das erfindungsgemäße Verfahren zeichnet sich durch kurze Trocknungszeiten aus und ergibt Feststoffisolationen mit einem Feuchtigkeitsgehalt kleiner 0,5%. Dies ist dadurch bedingt, daß durch den niederfrequenten Heizstrom die Wicklungsisola tionen des Transformators unter Vakuum und ohne die Anwesenheit von Öl auf hohe Temperaturen aufgeheizt werden und einen Teil ihrer Wärme durch Strahlung an die zwischen den Isolationen von Unter- und Oberspannungswicklungen angeordneten Barrieren isolationen sowie an das Öl des Transformators abgeben. Daher wird auch das Öl rascher aufgeheizt als bei einem Verfahren nach dem Stand der Technik, bei dem das Öl ausschließlich außerhalb des Transformators in einer Aufbereitungsanlage erwärmt wird. Da den Wicklungsisolationen von der Innenseite her Wärme zugeführt wird, können die zu entfernenden Gase und Dämpfe besonders leicht nach außen diffundieren. Die Fest stoffisolationen können daher unter Öl gut vorgetrocknet werden. Parallel dazu kann das Öl in einer außerhalb des Transformatorgehäuses angeordneten Ölaufbereitungsanlage aufbereitet werden. Hierbei können in Abhängigkeit von der Ölzusammensetzung Trocknungstemperaturen von 80 bis 90°C erreicht werden. Bei Endtrocknungen unter Vakuum können dann in Abhängigkeit von der Materialzusammensetzung der Feststoff isolationen Trocknungstemperaturen von 110 bis 120°C erreicht werden.The inventive method is characterized by short Drying times and gives solid insulation with a Moisture content less than 0.5%. This is because that the winding insulation due to the low-frequency heating current tion of the transformer under vacuum and without the presence be heated by oil to high temperatures and some their heat by radiation to the between the insulation of Under and high voltage windings arranged barriers Give insulation and to the oil of the transformer. Therefore the oil is also heated up more quickly than with a process according to the state of the art, where the oil is exclusively outside the transformer in a processing plant is heated. Because the winding insulation from the inside forth heat is supplied, the gases to be removed and Diffuse vapors particularly easily to the outside. The feast Insulations can therefore be pre-dried well under oil will. In parallel, the oil can be in an outside of the Transformer housing arranged oil treatment system be processed. Depending on the Oil composition drying temperatures from 80 to 90 ° C can be achieved. When drying under vacuum can then Depends on the material composition of the solid Insulations Drying temperatures of 110 to 120 ° C reached will.
Das erfindungsgemäße Verfahren benötigt zudem relativ wenig Energie, da nach der Vortrocknung der Feststoffisolationen im Öl und nach Ablassen des Öls nur noch die Wicklungen, die Wicklungsisolationen und die Barrierenisolation auf eine hohe Temperatur (110 bis 120°C) aufgeheizt und bei dieser Temperatur unter Vakuum bzw. bei Unterdruck über einen längeren Zeitraum gehalten werden. Dies vor allem deshalb, weil unter Vakuum bzw. bei Unterdruck nur-relativ wenig Wärme und zwar lediglich durch Strahlung verloren geht. Da die Endtrocknung der Feststoff isolationen unter Vakuum bei hohen Temperaturen erfolgt, sind auch die Pumpzeiten für eine Vakuumpumpe zum Trocknen der Fest stoffisolationen und die Laufzeiten der Ölaufbereitungsanlage relativ kurz.The method according to the invention also requires relatively little Energy, because after the pre-drying of the solid insulation in the Oil and after draining the oil only the windings that Winding insulation and the barrier insulation to a high Temperature (110 to 120 ° C) heated up and at this temperature under vacuum or under vacuum over a longer period of time being held. This is mainly because under vacuum or with negative pressure only relatively little heat and only through Radiation is lost. Because the final drying of the solid Insulations are carried out under vacuum at high temperatures also the pumping times for a vacuum pump to dry the hard fabric insulation and the running times of the oil treatment plant relatively short.
Zugleich zeichnet sich das erfindungsgemäße Verfahren durch hohe Betriebssicherheit und hohen Bedienungskomfort aus, da basierend auf den das Verfahren beeinflussenden Parametern, wie Leistung des Transformators, Größe der Oberspannung, Art der Wicklungsmaterialien, z. B. Kupfer oder Aluminium, erwünschte Aufheizleistung, erwünschter Heizstrom und erwünschte Trock nungstemperatur, der Trocknungsprozeß in allen kritischen Prozeßphasen vollautomatisch gesteuert und überwacht werden kann. Falls der Heizstrom zu groß werden sollte oder falls in einer der Phasen des Heizstromes, etwa infolge eines fehler haften Stromanschlusses, ein abweichender Strom fließt, so kann dies visuell und/oder akustisch gemeldet und der Heizstrom abgeschaltet werden. At the same time, the inventive method is characterized high operational reliability and ease of use, because based on the parameters influencing the process, such as Power of the transformer, size of the high voltage, type of Winding materials, e.g. As copper or aluminum, desired Heating output, desired heating current and desired drying temperature, the drying process in all critical Process phases are controlled and monitored fully automatically can. If the heating current should become too large or if in one of the phases of the heating current, for example as a result of an error stick to the power connection, a different current flows, so this can be visually and / or acoustically reported and the heating current be switched off.
In den Zeichnungen ist ein Ausführungsbeispiel der Erfindung vereinfacht dargestellt, und zwar zeigt:In the drawings is an embodiment of the invention shown in simplified form, namely:
Fig. 1 ein Blockschaltbild eines Leistungstransformators und einer Vorrichtung zur Trocknung der Feststoffisola tionen dieses Transformator gemäß dem erfindungs gemäßen Verfahrens, und Fig. 1 is a block diagram of a power transformer and a device for drying the solid Isolations tion of this transformer according to the method according to the Invention, and
Fig. 2 ein Diagramm, in dem wichtige Parameter des erfindungsgemäßen Verfahrens, wie niederfrequenter Heizstrom ILF (angegeben in Bruchteilen des Transformatornennstroms IN), im Gehäuse des Transformators herrschender Druck p [mbar] und herrschende Temperaturen T [°C] sowie aus dem Gehäuse entfernte Wassermenge mWASSER, in Funktion der Zeit angegeben sind. Fig. 2 is a diagram in which important parameters of the method according to the invention, such as low-frequency heating current I LF (specified in fractions of the nominal transformer current I N ), pressure p [mbar] and temperature T [° C.] in the housing of the transformer and from the Housing removed amount of water m WATER , are given as a function of time.
In Fig. 1 bezeichnet 1 das vakuumdichte, an eine Vakuumpumpe 2 angeschlossene Gehäuse des Transformators. Das Bezugszeichen 3 bezieht sich auf eine Aufbereitungsvorrichtung für Isolieröl. Diese Aufbereitungsvorrichtung weist einen nicht bezeichneten Eingang auf, welcher über eine Ölleitung 4 mit einem nicht bezeichneten Ausgang des Gehäuses 1 verbunden ist, sowie einen nicht bezeichneten Ausgang, welcher über eine Ölleitung 5 mit einem nicht bezeichneten Eingang des Gehäuses 1 verbunden ist. 6 bezeichnet einen Regeltransformator, der auf einen Frequenz wandler 7 wirkt. Vom Frequenzwandlern 7 ausgehende dreiphasige Stromzuführungen 8 werden von Strom- und Spannungswandlern 9 überwacht und sind über Gehäusedurchführungen 10 an im Inneren des Transformatorgehäuses 1 befindliche, nicht dargestellte Oberspannungswicklungen geführt. Ebenfalls nicht ersichtlich sind die Unterspannungswicklungen des Transformators, deren Stromanschlüsse über Gehäusedurchführungen 11 nach außen geführt und ersichtlich kurzgeschlossen sind.In Fig. 1 1, the vacuum-tight, connected to a vacuum pump housing 2 denotes the transformer. The reference number 3 relates to a processing device for insulating oil. This processing apparatus comprises an input is not designated on, which is connected via an oil line 4 with a non-designated output of the casing 1, and an output, not designated, which is connected via an oil line 5 with a non-designated input of the housing. 1 6 denotes a control transformer, which acts on a frequency converter 7 . Three-phase current leads 8 starting from the frequency converter 7 are monitored by current and voltage converters 9 and are guided via housing bushings 10 to high-voltage windings (not shown ) located in the interior of the transformer housing 1 . Also not visible are the undervoltage windings of the transformer, the current connections of which are routed to the outside via housing bushings 11 and are evidently short-circuited.
Eine Steuereinheit 12 dient der zentralen Erfassung und Verarbeitung von Mess-Signalen, die von nicht dargestellten Sensoren abgegeben werden, welche im Leistungstransformator und in der Trocknungsvorrichtung angeordnet sind. Die Steuereinheit 12 bildet aus den erfaßten Mess-Signalen Steuersignale, welche auf Stellglieder der vorgenannten Komponenten wirken. Die Sensoren befinden sich beispielsweise im Transformatorgehäuse 1 und dienen der Messung des Drucks im Gehäuse inneren oder der Temperatur von im Gehäuse 1 befindlichem Isolieröl. Weitere Sensoren sind die Strom- und Spannungswandler 9. Stellglieder befinden sich an der Vakuumpumpe 2, der Aufbereitungsvorrich tung 3, dem Regeltransformator 6 und den Frequenzwandlern 7. Mit der Steuereinheit 12 kann über einen Rechner 13 mit Peripheriegeräten 14, wie Drucker und Bildschirm, kommuniziert werden.A control unit 12 serves for the central acquisition and processing of measurement signals which are emitted by sensors, not shown, which are arranged in the power transformer and in the drying device. The control unit 12 forms control signals from the detected measurement signals, which act on actuators of the aforementioned components. The sensors are located, for example, in transformer housing 1 and are used to measure the pressure inside the housing or the temperature of insulating oil located in housing 1 . Other sensors are the current and voltage converters 9 . Actuators are located on the vacuum pump 2 , the conditioning device 3 , the control transformer 6 and the frequency converters 7 . The control unit 12 can be used to communicate with peripheral devices 14 , such as printer and monitor, via a computer 13 .
Bei der Durchführung des Verfahrens wird zunächst eine Vortrocknungsphase durchschritten. Hierbei werden die Wicklun gen mit niederfrequentem Heizstrom von typischerweise 3 bis 5 Hz mit einer Größe, welche nur einem Bruchteil des Nennstroms IN des Transformators entspricht, aufgeheizt. Der Heizstrom fließt hierbei lediglich durch die Oberspannungswicklungen. Durch Induktion wird aber auch in den kurzgeschlossenen Unter spannungswicklungen ein Heizstrom hervorgerufen, so daß die gesamten Wicklungen und damit auch alle Feststoffisolationen des Transformators aufgeheizt werden. Während des Heizens wird fortlaufend die mittlere Wicklungstemperatur der Transformator wicklungen erfaßt. Dies kann beispielsweise mit einem im Stand der Technik nach der EP 0 543 181 B1 beschriebenen Widerstands meßgerät oder aber auch über Messung von Strom und Spannung des Heizstroms ermittelt werden. When the process is carried out, a pre-drying phase is carried out. Here, the windings are heated with a low-frequency heating current of typically 3 to 5 Hz with a size that corresponds to only a fraction of the nominal current I N of the transformer. The heating current only flows through the high-voltage windings. By induction, however, a heating current is also generated in the short-circuited under-voltage windings, so that the entire windings and thus all solid insulation of the transformer are heated. During the heating, the average winding temperature of the transformer windings is continuously recorded. This can be determined, for example, using a resistance measuring device described in the prior art according to EP 0 543 181 B1 or else by measuring the current and voltage of the heating current.
Der Temperaturverlauf der mittleren Wicklungstemperatur ist in Fig. 2 in Funktion der Zeit dargestellt und mit TW bezeichnet. Der zeitliche Verlauf des von den Strom- und Spannungswandlern 9 ermittelten niederfrequenten Heizstroms ist in Fig. 2 mit ILF bezeichnet. Erfaßt in Fig. 2 sind ferner auch der zeitliche Verlauf der Temperatur TÖ des Transformatoröls, der zeitliche Verlauf des im Inneren des Transformatorgehäuses herrschenden Gasdrucks pG (zwei Varianten sind dargestellt) und der zeitli che Verlauf der Menge mWasser des aus den Feststoffisolationen austretenden Wassers, welche lediglich in relativen Einheiten angegeben ist.The temperature curve of the average winding temperature is shown in FIG. 2 as a function of time and is denoted by T W. The time course of the low-frequency heating current determined by the current and voltage converters 9 is designated in FIG. 2 by I LF . Detected in Fig. 2 are furthermore also the variation of the temperature T E of the transformer oil, the temporal course of the pressure prevailing in the interior of the transformer housing gas pressure p G (two variants are shown) and exiting the zeitli che course of the amount m of water of from the solid insulation Water, which is only given in relative units.
Parallel zum Heizen der Wicklungen wird das im Gehäuse 1 befindliche Isolieröl hauptsächlich in der Aufbereitungs vorrichtung 3 aufgeheizt. Zu diesem Zweck wird das Isolieröl sukzessive aus dem Gehäuseinneren über die Ölleitung 4 zur Aufbereitungsvorrichtung 3 gepumpt, dort je nach Ölzusammen setzung auf eine zulässige obere Öltemperatur von ca. 70 bis 80°C, beispielsweise 80°C, erwärmt, entgast und entwässert und dann über die Ölleitung 5 ins Gehäuse zurückgepumpt. Das Öl wird im allgemeinen im Gehäuse 1 umgewälzt, es kann aber auch ins Gehäuse 1 eingesprüht werden. In jedem Fall kontaktiert es das Transformatorgehäuse und die Feststoffisolationen und nimmt dabei als den Isolationen tretende Feuchtigkeit und Gase auf, welche durch nachfolgendes Entgasen und Entwässern des Öls in der Aufbereitungsvorrichtung 3 entfernt werden.In parallel to the heating of the windings, the insulating oil located in the housing 1 is mainly heated in the preparation device 3 . For this purpose, the insulating oil is successively pumped from the interior of the housing via the oil line 4 to the treatment device 3 , there, depending on the oil composition, to a permissible upper oil temperature of approximately 70 to 80 ° C, for example 80 ° C, heated, degassed and dewatered and then pumped back into the housing via the oil line 5 . The oil is generally circulated in the housing 1 , but it can also be sprayed into the housing 1 . In any case, it contacts the transformer housing and the solid insulation and thereby absorbs moisture and gases emerging from the insulation, which are removed by subsequent degassing and dewatering of the oil in the treatment device 3 .
Zum Zeitpunkt t₁, welcher je nach Größe des Transformators bis zu 20 Stunden betragen kann, sind die Wicklungen auf eine erste mittlere Wicklungstemperatur von typischerweise 90 bis 100°C, beispielsweise 100°C, aufgeheizt. Das Transformatoröl weist dann eine Temperatur von ca. 60°C auf. Der Druck im Gehäuse inneren kann dann noch Atmosphärendruck sein, kann aber auch zu Zwecken einer besonders guten Entgasung und Entwässerung des Öls mittels der Vakuumpumpe 2 erheblich, beispielsweise auf 200 mbar, abgesenkt sein (Varianten in Fig. 2). Die Größe des Heiz stroms wird nun so stark reduziert, daß die Wicklungen auf der ersten Wicklungstemperatur gehalten werden. Es kann sich nun eine gleichmäßige Temperaturverteilung in der Feststoff isolationen einstellen. Gleichzeitig wird das Öl weiter erwärmt und aufbereitet.At the time t 1, which can be up to 20 hours depending on the size of the transformer, the windings are heated to a first average winding temperature of typically 90 to 100 ° C, for example 100 ° C. The transformer oil then has a temperature of approx. 60 ° C. The pressure inside the housing can then still be atmospheric pressure, but can also be reduced considerably, for example to 200 mbar, for the purposes of particularly good degassing and dewatering of the oil by means of the vacuum pump 2 (variants in FIG. 2). The size of the heating current is now reduced so much that the windings are kept at the first winding temperature. A uniform temperature distribution in the solid insulation can now occur. At the same time, the oil is further heated and processed.
Bei Erreichen der oberen Öltemperatur von typischerweise 80°C zum Zeitpunkt t₂ ist die Menge des aus den Feststoffisolationen austretenden Wassers relativ klein. Die Vortrocknungsphase ist nun abgeschlossen. Das Öl wird sodann vollständig aus dem Transformatorgehäuse 1 gepumpt. Gleichzeitig wird das Gehäuse 1 evakuiert und der Heizstrom auf einen Wert vergrößert, der ausreicht, um den überwiegenden Teil von in den Feststoffiso lationen vorhandenem Wasser zu verdampfen. Dieses Wasser wird durch die Vakuumpumpe 2 und/oder die Aufbereitungsvorrichtung 3 abgesaugt. Durch den erhöhten Heizstrom erwärmen sich die Wicklungen zusätzlich.When the upper oil temperature of typically 80 ° C at time t₂ is reached, the amount of water emerging from the solid insulation is relatively small. The pre-drying phase is now complete. The oil is then pumped completely out of the transformer housing 1 . At the same time, the housing 1 is evacuated and the heating current is increased to a value which is sufficient to evaporate the majority of the water present in the solid insulation. This water is sucked off by the vacuum pump 2 and / or the treatment device 3 . The windings also heat up due to the increased heating current.
Zum Zeitpunkt t₃ sind die Wicklungen auf eine zweite mittlere Wicklungstemperatur aufgeheizt, welche je nach Ausbildung der Isolation zwischen 110 bis 120°C, beispielsweise bei 115°C, liegt. Der Heizstrom wird nun wieder reduziert und zwar so, daß die zweite Wicklungstemperatur beibehalten wird. Dies wird mit besonderem Vorteil dadurch erreicht, daß der Heizstrom pulsierend zugeführt wird. Während dieser Zeit wird ersichtlich der größte Teil der unerwünschten Feuchtigkeit (Kurve mWASSER) durch die Vakuumpumpe 2 und/oder die Aufbereitungsvorrichtung aus den Feststoffisolationen entfernt. Die niedrige Frequenz des Heizstroms ermöglicht den Einsatz niedriger Heizspannungen. Durch das im Gehäuse herrschende Vakuum begünstigte elektrische Überschläge an den Feststoffisolationen werden so vermieden.At time t₃, the windings are heated to a second average winding temperature, which, depending on the design of the insulation, is between 110 to 120 ° C, for example at 115 ° C. The heating current is now reduced again so that the second winding temperature is maintained. This is achieved with particular advantage in that the heating current is supplied in a pulsating manner. During this time, the major part of the undesired moisture (curve m WATER ) is evidently removed from the solid insulation by the vacuum pump 2 and / or the processing device. The low frequency of the heating current enables the use of low heating voltages. This prevents electrical flashovers on the solid insulation that favor the vacuum in the housing.
Sobald das Vakuum im Gehäuse 1 einen vorgegebenen Grenzwert von beispielsweise 0,5 bis 5 mbar unterschreitet, oder wenn inner halb einer vorgegebenen Zeitspanne ein vorgegebener Druck gehalten wird, wird der Heizstrom zum Zeitpunkt t₄ unterbro chen. Das parallel zum Trocknen der Feststoffisolationen aufbereitete Öl kann nun eingefüllt werden. Die Zeitdauer des Trocknungsvorganges ist ca. 40 bis 60% kürzer als bei Verfahren nach dem Stand der Technik. Da die Wasserabdampfung bei wesentlich höheren Temperaturen erfolgt als bei Verfahren nach dem Stand der Technik, werden neben einer kurzen Trocknungszeit zugleich auch äußerst geringe Restwassermengen von weniger als 0,5 Gewichtsprozent in den Feststoffisolationen erreicht.As soon as the vacuum in the housing 1 falls below a predetermined limit value of, for example, 0.5 to 5 mbar, or if a predetermined pressure is maintained within a predetermined time span, the heating current is interrupted at the time t₄. The oil that is processed in parallel with the drying of the solid insulation can now be filled in. The drying process is approximately 40 to 60% shorter than in the prior art processes. Since the water is evaporated at much higher temperatures than in prior art processes, in addition to a short drying time, extremely small amounts of residual water of less than 0.5 percent by weight are also achieved in the solid insulation.
Um ein zu starkes Aufheizen der Wicklungen mit Sicherheit zu vermeiden, wird kurz vor Erreichen der zweiten mittleren Wick lungstemperatur zusätzlich auch die mittlere Temperatur der Oberspannungswicklungen, etwa über das vorgenannte Widerstands- Meßgerät ermittelt. Liegt die durch Vergleich der mittleren Temperaturen von Oberspannungswicklungen und Transformatorwick lungen ermittelte Temperatur unterhalb der Solltemperatur der Oberspannungswicklungen, so wird der Heizstrom auf sehr tiefe Frequenzen, beispielsweise 0,05 Hz, heruntergefahren und werden nur noch die Oberspannungswicklungen mit dem sehr niederfre quenten Strom bzw. mit dem Gleichstrom nachgeheizt.To surely overheat the windings avoid, will shortly before reaching the second middle wick also the mean temperature of the High-voltage windings, for example via the aforementioned resistance Measuring device determined. Is the comparison of the middle Temperatures of high voltage windings and transformer windings temperature determined below the set temperature of the High-voltage windings, so the heating current is very low Frequencies, for example 0.05 Hz, are shut down and are only the high voltage windings with the very low fre quent current or reheated with the direct current.
Durch geeignet angeordnete und verteilte Schaltstellen kann es ermöglicht werden, daß die mittlere Temperatur mindestens einer der Oberspannungswicklungen unabhängig von den mittleren Temperaturen der restlichen Oberspannungswicklungen gemessen wird. Liegt die Temperatur der vermessenen Oberspannungswick lung noch unter ihrer Solltemperatur, so wird diese Wicklung unabhängig von den restlichen Oberspannungswicklungen nachgeheizt.It can be done by suitably arranged and distributed switching points be made possible that the mean temperature at least one of the high voltage windings regardless of the middle one Temperatures of the remaining high-voltage windings measured becomes. Is the temperature of the measured high voltage winding still below its set temperature, this winding regardless of the remaining high-voltage windings reheated.
Entsprechend den mittleren Wicklungstemperaturen können die mittleren Temperaturen jeder Ober- oder jeder Unterspannungs wicklung aus einer Messung von Strom und Spannung des Heiz stroms oder aus einer Messung des elektrischen Widerstands der Ober- oder Unterspannungswicklung ermittelt werden. Alternativ oder zusätzlich ist es auch möglich, diese Temperaturen durch Sensoren zu ermitteln, welche durch das Transformatorgehäuse an die betreffenden Wicklungen geführt sind. According to the average winding temperatures, the average temperatures of any high or low voltage winding from a measurement of the current and voltage of the heating current or from a measurement of the electrical resistance of the Over- or undervoltage winding can be determined. Alternatively or in addition it is also possible to go through these temperatures Sensors to determine which through the transformer housing the windings in question are guided.
Eine besonders schonende Trocknung der Feststoffisolationen wird erreicht, wenn die Wicklungen durch Anpassung des Heiz stroms stufenweise auf einer dritten mittleren Wicklungs temperatur und gegebenenfalls auf weiteren mittleren Wicklungstemperaturen gehalten werden, wobei diese mittleren Wicklungstemperaturen jeweils zwischen der ersten und der zweiten mittleren Wicklungstemperatur liegen.A particularly gentle drying of the solid insulation is achieved when the windings by adjusting the heating currents gradually on a third middle winding temperature and, if necessary, on further average Winding temperatures are kept, these mean Winding temperatures between the first and the second average winding temperature.
BezugszeichenlisteReference list
1 Gehäuse
2 Vakuumpumpe
3 Aufbereitungsvorrichtung
4, 5 Ölleitung
6 Regeltransformator
7 Frequenzwandler
8 Stromzuführungen
9 Strom- und Spannungswandler
10, 11 Durchführungen
12 Steuereinheit
13 Rechner
14 Peripheriegeräte. 1 housing
2 vacuum pump
3 processing device
4 , 5 oil pipe
6 control transformer
7 frequency converters
8 power supplies
9 current and voltage transformers
10 , 11 bushings
12 control unit
13 computers
14 peripheral devices.
Claims (13)
daß bei kurzgeschlossenen Unterspannungswicklungen die Wicklungen mittels eines in den Oberspannungswicklungen geführten niederfrequenten Heizstromes auf eine erste mittlere Wicklungstemperatur aufgeheizt werden (Zeitpunkt t₁) ,
daß die Feststoffisolationen bei dieser Temperatur im Öl solange vorgetrocknet werden, bis das Öl auf eine unter halb der ersten mittleren Wicklungstemperatur liegende obere Öltemperatur erwärmt ist (Zeitpunkt t₂),
daß nach Erreichen der oberen Öltemperatur das aufberei tete Öl aus dem Transformatorgehäuse (1) entfernt und die Wicklungen unter Vakuum oder bei Unterdruck im ölfreien Transformatorgehäuse (1) mittels des niederfrequenten Heizstroms auf eine zweite mittlere Wicklungstemperatur, welche höher ist als die erste mittlere Wicklungstempera tur, aufgeheizt werden (Zeitpunkt t₃) und
daß die Feststoffisolationen bei der zweiten mittleren Wicklungstemperatur unter Vakuum oder bei Unterdruck vollständig getrocknet werden (Zeitpunkt t₄).1. A process for drying the solid insulation of a transformer arranged in an electrical installation, in which the solid insulation is contacted with heated transformer oil, and the transformer oil contacted with the solid insulation is degassed and / or dewatered, characterized in that
that in the case of short-circuited undervoltage windings, the windings are heated to a first mean winding temperature by means of a low-frequency heating current conducted in the high-voltage windings (time t 1),
that the solid insulation is pre-dried at this temperature in the oil until the oil is heated to an upper oil temperature below half the first average winding temperature (time t₂),
that after reaching the upper oil temperature the processed oil removed from the transformer housing ( 1 ) and the windings under vacuum or under vacuum in the oil-free transformer housing ( 1 ) by means of the low-frequency heating current to a second average winding temperature, which is higher than the first average winding temperature , are heated (time t₃) and
that the solid insulation at the second average winding temperature under vacuum or under vacuum are completely dried (time t₄).
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE1995101323 DE19501323C2 (en) | 1995-01-19 | 1995-01-19 | Process for drying the solid insulation of a transformer arranged in an electrical system |
CH265995A CH690211A5 (en) | 1995-01-19 | 1995-09-20 | The method for drying the solid insulation of a arranged in an electrical system transformer. |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE1995101323 DE19501323C2 (en) | 1995-01-19 | 1995-01-19 | Process for drying the solid insulation of a transformer arranged in an electrical system |
Publications (2)
Publication Number | Publication Date |
---|---|
DE19501323A1 true DE19501323A1 (en) | 1996-07-25 |
DE19501323C2 DE19501323C2 (en) | 2003-10-09 |
Family
ID=7751724
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE1995101323 Expired - Lifetime DE19501323C2 (en) | 1995-01-19 | 1995-01-19 | Process for drying the solid insulation of a transformer arranged in an electrical system |
Country Status (2)
Country | Link |
---|---|
CH (1) | CH690211A5 (en) |
DE (1) | DE19501323C2 (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE10035948A1 (en) * | 2000-07-21 | 2002-02-07 | Alstom | Drying cellulosic insulation of transformer or choke, involves introducing hot gas into transformer vessel, then evacuating it |
EP1253389A1 (en) * | 2001-04-24 | 2002-10-30 | Micafil Ag | Process for drying an active part, and apparatus for carrying out this process |
US6634117B2 (en) | 2001-04-24 | 2003-10-21 | Micafil Ag | Method for drying an active part and device for carrying out this method |
US8056256B2 (en) | 2008-09-17 | 2011-11-15 | Slack Associates, Inc. | Method for reconditioning FCR APG-68 tactical radar units |
US8082681B2 (en) | 2008-10-22 | 2011-12-27 | Slack Associates, Inc. | Method for improving or reconditioning FCR APG-68 tactical radar units |
DE102010045239A1 (en) | 2010-09-08 | 2012-03-08 | Siemens Aktiengesellschaft | Method and arrangement for drying a transformer component |
US8505212B2 (en) | 2008-09-17 | 2013-08-13 | Slack Associates, Inc. | Method for reconditioning or processing a FCR APG-68 tactical radar unit |
CN103840675A (en) * | 2014-02-27 | 2014-06-04 | 苏州华电电气股份有限公司 | Low-frequency heating device of transformer |
CN103874242A (en) * | 2014-03-19 | 2014-06-18 | 国家电网公司 | Large power transformer low-frequency heating device and achieving method |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US8701307B2 (en) | 2008-09-17 | 2014-04-22 | Howard C. Slack | Method for cleaning and reconditioning FCR APG-68 tactical radar units |
CN102722193B (en) * | 2012-06-25 | 2014-02-19 | 甘景福 | Method for slowing down aging of solid insulation of oil-paper insulating transformer |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2358072A1 (en) * | 1972-11-23 | 1974-06-06 | British Oxygen Co Ltd | OIL-INSULATED ELECTRIC TRANSFORMER |
EP0543181A1 (en) * | 1991-11-18 | 1993-05-26 | MICAFIL Vakuumtechnik AG | Method of producing transformers, especially transformers for distribution installations, and apparatus therefor |
-
1995
- 1995-01-19 DE DE1995101323 patent/DE19501323C2/en not_active Expired - Lifetime
- 1995-09-20 CH CH265995A patent/CH690211A5/en not_active IP Right Cessation
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2358072A1 (en) * | 1972-11-23 | 1974-06-06 | British Oxygen Co Ltd | OIL-INSULATED ELECTRIC TRANSFORMER |
EP0543181A1 (en) * | 1991-11-18 | 1993-05-26 | MICAFIL Vakuumtechnik AG | Method of producing transformers, especially transformers for distribution installations, and apparatus therefor |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE10035948A1 (en) * | 2000-07-21 | 2002-02-07 | Alstom | Drying cellulosic insulation of transformer or choke, involves introducing hot gas into transformer vessel, then evacuating it |
EP1253389A1 (en) * | 2001-04-24 | 2002-10-30 | Micafil Ag | Process for drying an active part, and apparatus for carrying out this process |
US6634117B2 (en) | 2001-04-24 | 2003-10-21 | Micafil Ag | Method for drying an active part and device for carrying out this method |
CZ300982B6 (en) * | 2001-04-24 | 2009-09-30 | Abb Schweiz Ag | Process for drying an active part containing at least one winding and apparatus for making the same |
US8505212B2 (en) | 2008-09-17 | 2013-08-13 | Slack Associates, Inc. | Method for reconditioning or processing a FCR APG-68 tactical radar unit |
US8056256B2 (en) | 2008-09-17 | 2011-11-15 | Slack Associates, Inc. | Method for reconditioning FCR APG-68 tactical radar units |
US8082681B2 (en) | 2008-10-22 | 2011-12-27 | Slack Associates, Inc. | Method for improving or reconditioning FCR APG-68 tactical radar units |
DE102010045239A1 (en) | 2010-09-08 | 2012-03-08 | Siemens Aktiengesellschaft | Method and arrangement for drying a transformer component |
WO2012031791A1 (en) | 2010-09-08 | 2012-03-15 | Siemens Aktiengesellschaft | Method and arrangement for drying a transformer component |
DE102010045239B4 (en) * | 2010-09-08 | 2012-10-04 | Siemens Aktiengesellschaft | Method and arrangement for drying a transformer component |
CN103840675A (en) * | 2014-02-27 | 2014-06-04 | 苏州华电电气股份有限公司 | Low-frequency heating device of transformer |
CN103874242A (en) * | 2014-03-19 | 2014-06-18 | 国家电网公司 | Large power transformer low-frequency heating device and achieving method |
CN103874242B (en) * | 2014-03-19 | 2015-11-11 | 国家电网公司 | A kind of implementation method of large-scale power transformer low frequency heating |
Also Published As
Publication number | Publication date |
---|---|
DE19501323C2 (en) | 2003-10-09 |
CH690211A5 (en) | 2000-05-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE19501323C2 (en) | Process for drying the solid insulation of a transformer arranged in an electrical system | |
DE3606697C2 (en) | Procedure for checking the damage to the insulation of a high-voltage cable | |
DE2516783C3 (en) | Drainage device for an explosion-proof electric motor | |
EP3245726B1 (en) | Arrangement having a converter | |
DE10127276B4 (en) | Underwater transformer and method for adjusting the pressure in the outer vessel of an underwater transformer | |
EP0543181A1 (en) | Method of producing transformers, especially transformers for distribution installations, and apparatus therefor | |
WO2020193064A1 (en) | Housing assembly | |
EP3504721B1 (en) | Mobile transformer bushing terminal | |
EP0801405B1 (en) | Process for predrying a coil block containing at least one winding and solid insulation and devices for carrying out this process | |
EP0831575A1 (en) | Method and apparatus for manufacturing conductive bars arranged preferably in the form of roebel bars | |
EP3283833A1 (en) | Method for drying a gas chamber and arrangement comprising a protective-gas filled chamber | |
EP1253389B1 (en) | Process for drying an active part, and apparatus for carrying out this process | |
DE2358068C3 (en) | Device for vacuum degassing of liquids | |
EP3726547B1 (en) | Method for drying a transformer comprising a multi-stage cooling system and cooling system control for such a transformer | |
EP2665838B1 (en) | Process for heating and drying a good | |
WO2017137193A1 (en) | High-voltage device | |
CH699528B1 (en) | Method for drying active component of e.g. transducer, involves spraying hot air from air heater dried during heat-up phase and/or medium vacuum phase into chamber, and guiding air from chamber into interior of autoclave through insulation | |
DE2358067A1 (en) | PROCEDURE FOR DRYING ELECTRIC OR OTHER EQUIPMENT | |
DE10224186A1 (en) | Switch enclosed by insulation/cooling liquid for electrical transformer, has switch housing, balancing vessel forming unit hermetically sealed to ambient air, and arrangement for temporarily opening to ambient air if level low | |
EP2019397A2 (en) | Electric transformer | |
EP2460163A1 (en) | Method for reducing the moisture of an insulation-coated winding and a spraying device for reducing moisture | |
DE3941362C2 (en) | Decontamination process for contaminated transformers | |
DE944968C (en) | Process for removing moisture | |
DE19826682A1 (en) | Evaporation of fluids in hygroscopic electrical insulation material | |
DE112020007246T5 (en) | HEAT TREATMENT DEVICE AND HEAT TREATMENT METHOD |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
OM8 | Search report available as to paragraph 43 lit. 1 sentence 1 patent law | ||
8128 | New person/name/address of the agent |
Representative=s name: LUECK, G., DIPL.-ING. DR.RER.NAT., PAT.-ANW., 7976 |
|
8128 | New person/name/address of the agent |
Representative=s name: ZIMMERMANN & PARTNER, 80331 MUENCHEN |
|
8141 | Disposal/no request for examination | ||
8127 | New person/name/address of the applicant |
Owner name: MICAFIL AG, ZUERICH, CH |
|
8110 | Request for examination paragraph 44 | ||
8170 | Reinstatement of the former position | ||
8304 | Grant after examination procedure | ||
8364 | No opposition during term of opposition | ||
8327 | Change in the person/name/address of the patent owner |
Owner name: ABB SCHWEIZ AG, BADEN, CH |
|
R071 | Expiry of right | ||