CN105180896A - Sandy soil pipeline settlement monitoring method - Google Patents

Sandy soil pipeline settlement monitoring method Download PDF

Info

Publication number
CN105180896A
CN105180896A CN201510607790.4A CN201510607790A CN105180896A CN 105180896 A CN105180896 A CN 105180896A CN 201510607790 A CN201510607790 A CN 201510607790A CN 105180896 A CN105180896 A CN 105180896A
Authority
CN
China
Prior art keywords
monitoring
accumulator
sandy soil
pipeline
monitoring method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510607790.4A
Other languages
Chinese (zh)
Inventor
时小兵
鲍金永
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201510607790.4A priority Critical patent/CN105180896A/en
Publication of CN105180896A publication Critical patent/CN105180896A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C5/00Measuring height; Measuring distances transverse to line of sight; Levelling between separated points; Surveyors' levels
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J7/00Circuit arrangements for charging or depolarising batteries or for supplying loads from batteries

Abstract

The invention discloses a sandy soil pipeline settlement monitoring method. The method comprises the steps of 1, installing a monitoring device, wherein a pipe clamp hoop is fixed to a buried pipeline, a fixed rod is vertically welded to the pipe clamp hoop, an instrument protection platform is arranged at the top end of the fixed rod, and a displacement sensing signal generator is placed in the instrument protection platform; 2, installing a signal reception and feedback tower; 3, installing a signal terminal processor, wherein a signal receiving and processing terminal is installed in a monitoring room so as to give an alarm and mark the position of a monitor point where an error occurs when the error is found out; 4, conducting examination, repair and maintenance by maintenance workers, wherein by means of the alarm given by the signal receiving and processing terminal and the marked position of the monitor point, maintenance workers go to the site for examination in time and take specific measures. Compared with the prior art, the method has the advantage that displacement deviation points can be well found out in use, information can be fed back in time, and real-time monitoring is achieved.

Description

A kind of sandy soil pipeline anti-settling monitoring method
Technical field
The invention belongs to monitoring pipeline's sedimentation technical field, particularly relate to a kind of sandy soil pipeline anti-settling monitoring method.
Background technology
At present, along with the emphasis of economic construction will advance further to NORTHWEST CHINA portion, exploitation great Northwest becomes China's Main Economic direction, and light industry, the heavy industry of country are progressively northwestwards tilted.Consider the geographical environment that northwestern is special, particularly the High aititude such as the Inner Mongol, Ningxia water-deficient area soil chiltern characteristic, to industrial construction, particularly the construction such as buried pipeline brings new problem.Consider that pipeline laying is in sandy soil layer, soil ability to resist splash erosion is weak, and the situation of subsiding in conduit running process happens occasionally, and brings in production, life dangerous to operating pipeline.
Summary of the invention
The object of the present invention is to provide a kind of sandy soil pipeline anti-settling monitoring method, to solve the problem proposed in above-mentioned background technology.
For achieving the above object, present invention employs following technical scheme:
A kind of sandy soil pipeline anti-settling monitoring method, comprises the following steps:
1) monitoring device is installed:
First with bolt, pipe clamp anchor ear is fixed on buried pipeline to be monitored, again fixed bar is vertically welded on pipe clamp anchor ear, then pipeline backfill is carried out, fixed bar top arranges protection of instrumentation platform, displacement sensing signal generator is placed in protection of instrumentation platform, accumulator is embedded near displacement sensing signal generator, by power lead, sensor signal generator is connected with accumulator, finally near accumulator, solar panel is installed, be charge in batteries by power lead after the sun power that solar panel is collected is converted into electric energy, complete the installation of a monitoring point like this, repeat above step and several monitoring points are in addition installed,
2) Signal reception feedback tower is installed:
Signal reception feedback tower is installed in the centre position of monitoring pipeline;
3) Signal Terminal processor is installed:
At monitoring indoor location Signal reception processing terminal, receive data of monitoring point constantly and contrast with raw data, making when finding error and report to the police and indicate the position, monitoring point occurring error;
4) service worker is checked, overhauls, is safeguarded:
By installing the warning of Signal reception processing terminal and indicating the position of monitoring point, service worker arrives scene in time and observes conditions, and makes concrete measure, prevents trouble before it happens.
Preferably, protection of instrumentation platform 1m at least above ground level.
Preferably, solar panel and accumulator are positioned at 2m around protection of instrumentation platform 3in scope.
Preferably, accumulator is positioned at apart from earth's surface below 0.5m.
Preferably, the distance of adjacent two monitoring points is 400-800m.
Compared with prior art, beneficial effect of the present invention is as follows:
The present invention is by passing through pipe clamp anchor ear by displacement sensing signal generator, fixed bar and protection of instrumentation platform are fixed on monitoring point, and provide required electric current with solar panel and accumulator to displacement sensing signal generator, and by Signal reception feedback tower, the Signal reception processing terminal of itself and rear end Control Room is realized wireless connections, pipe sedimentation is monitored by Signal reception processing terminal, compared with prior art, a kind of sandy soil pipeline anti-settling monitoring method proposed by the invention, not only rational in infrastructure, use well can find offset deviation point, feedback information timely, accomplish Real-Time Monitoring.
Accompanying drawing explanation
Fig. 1 is the scheme of installation of monitoring device in step 1).
Fig. 2 is the schematic diagram of sandy soil pipeline anti-settling monitoring method.
Embodiment
Below in conjunction with embodiment, optimal way of the present invention is described in further detail.
As depicted in figs. 1 and 2, a kind of sandy soil pipeline anti-settling monitoring method, comprises the following steps:
1) monitoring device is installed:
First with bolt, pipe clamp anchor ear 1 is fixed on buried pipeline to be monitored, again fixed bar 2 is vertically welded on pipe clamp anchor ear 1, then pipeline backfill is carried out, fixed bar 2 top arranges protection of instrumentation platform 3, protection of instrumentation platform 3 1m at least above ground level, displacement sensing signal generator 4 is placed in protection of instrumentation platform 3, accumulator 5 is embedded near displacement sensing signal generator 4, accumulator 5 is positioned at apart from earth's surface below 0.5m, by power lead, sensor signal generator 4 is connected with accumulator 5, finally near accumulator 5, solar panel 6 is installed, solar panel 6 and accumulator 5 are positioned at protection of instrumentation platform 3 surrounding 2m 3in scope, be that accumulator 5 charges, complete the installation of a monitoring point like this after the sun power that solar panel 6 is collected is converted into electric energy by power lead, repeat above step and install several monitoring points in addition, the distance of adjacent two monitoring points is 400-800m.
2) Signal reception feedback tower is installed:
Signal reception feedback tower 7 is installed in the centre position of monitoring pipeline.
3) Signal Terminal processor is installed:
At monitoring indoor location Signal reception processing terminal 8, receive data of monitoring point constantly and contrast with raw data, making when finding error and report to the police and indicate the position, monitoring point occurring error.
4) service worker is checked, overhauls, is safeguarded:
By installing the warning of Signal reception processing terminal 8 and indicating the position of monitoring point, service worker arrives scene in time and observes conditions, and makes concrete measure, prevents trouble before it happens.
Pipe clamp anchor ear 1 and fixed bar 2, protection of instrumentation platform 3 in use, time in buried pipeline is laid in sandy soil, are arranged on pipeline by the present invention together, ensure that protection of instrumentation platform 3 goes out ground 1m high when pipeline backfill completes.Solar panel 6 and accumulator 5 are arranged on protection of instrumentation platform 3 surrounding 2m 3in scope, accumulator 5 is imbedded apart from earth's surface below 0.5m.Displacement sensing signal generator 4 is placed in protection of instrumentation platform 3, utilizes power lead accumulator 5 and solar panel 6, accumulator 5 to be coupled together with displacement sensing signal generator 4.Repeat to install several monitoring points by above step, adjacent monitoring point distance controlling is between 400m-800m.
Behind installation monitoring point, Signal reception feedback tower 7 is installed in monitoring pipeline centre position, Signal reception feedback tower 7 receives constantly in order to the displacement point signal sent by monitoring point displacement sensing signal generator 4, and send Control Room Signal reception processing terminal 8 to, Signal reception processing terminal 8 is provided with piping displacement database, change in displacement data and raw data is contrasted constantly.Occur very little change for certain some displacement, Signal reception processing terminal 8 gives the alarm, and indicates concrete position, monitoring point.Maintenance personal according to circumstances, rushes to the scene and checks concrete condition, makes on-call maintenance maintenance measure.
Above embodiment is only be described the preferred embodiment of the present invention; not scope of the present invention is limited; under not departing from the present invention and designing the prerequisite of spirit; the various distortion that those of ordinary skill in the art make technical scheme of the present invention and improvement, all should fall in protection domain that claims of the present invention determines.

Claims (5)

1. a sandy soil pipeline anti-settling monitoring method, is characterized in that, comprise the following steps:
1) monitoring device is installed:
First with bolt, pipe clamp anchor ear (1) is fixed on buried pipeline to be monitored, again fixed bar (2) is vertically welded on pipe clamp anchor ear (1), then pipeline backfill is carried out, fixed bar (2) top arranges protection of instrumentation platform (3), displacement sensing signal generator (4) is placed in protection of instrumentation platform (3), accumulator (5) is embedded near displacement sensing signal generator (4), by power lead, sensor signal generator (4) is connected with accumulator (5), last installation solar panel (6) near accumulator (5), after the sun power that solar panel (6) is collected is converted into electric energy by power lead be accumulator (5) charging, complete the installation of a monitoring point like this, repeat above step and several monitoring points are in addition installed,
2) Signal reception feedback tower is installed:
In the centre position of monitoring pipeline, Signal reception feedback tower (7) is installed;
3) Signal Terminal processor is installed:
In monitoring indoor location Signal reception processing terminal (8), receive data of monitoring point constantly and contrast with raw data, making when finding error and report to the police and indicate the position, monitoring point occurring error;
4) service worker is checked, overhauls, is safeguarded:
By installing the warning of Signal reception processing terminal (8) and indicating the position of monitoring point, service worker arrives scene in time and observes conditions, and makes concrete measure, prevents trouble before it happens.
2. sandy soil pipeline anti-settling monitoring method according to claim 1, is characterized in that, described protection of instrumentation platform (3) 1m at least above ground level.
3. sandy soil pipeline anti-settling monitoring method according to claim 1, is characterized in that, described solar panel (6) and accumulator (5) are positioned at protection of instrumentation platform (3) 2m around 3in scope.
4. sandy soil pipeline anti-settling monitoring method according to claim 1, is characterized in that, described accumulator (5) is positioned at apart from earth's surface below 0.5m.
5. sandy soil pipeline anti-settling monitoring method according to claim 1, is characterized in that, the distance of adjacent two monitoring points is 400-800m.
CN201510607790.4A 2015-09-23 2015-09-23 Sandy soil pipeline settlement monitoring method Pending CN105180896A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510607790.4A CN105180896A (en) 2015-09-23 2015-09-23 Sandy soil pipeline settlement monitoring method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510607790.4A CN105180896A (en) 2015-09-23 2015-09-23 Sandy soil pipeline settlement monitoring method

Publications (1)

Publication Number Publication Date
CN105180896A true CN105180896A (en) 2015-12-23

Family

ID=54903149

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510607790.4A Pending CN105180896A (en) 2015-09-23 2015-09-23 Sandy soil pipeline settlement monitoring method

Country Status (1)

Country Link
CN (1) CN105180896A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6169387B1 (en) * 1997-12-22 2001-01-02 Lifecor, Inc. Battery management apparatus for portable electronic devices
CN101158865A (en) * 2007-11-13 2008-04-09 中国移动通信集团福建有限公司 Electricity generator monitoring system device
CN102636147A (en) * 2012-03-31 2012-08-15 铁道第三勘察设计院集团有限公司 Deformation monitoring method for existing railway line
CN103115788A (en) * 2012-11-20 2013-05-22 上海理工大学 Indoor model experience device with existing tunnel affected by double subway construction
CN103196421A (en) * 2013-01-22 2013-07-10 中交天津港湾工程研究院有限公司 Automatic inspection type layered settlement instrument
CN103363954A (en) * 2013-07-22 2013-10-23 广西土木勘察检测治理有限公司 Land subsidence monitoring system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6169387B1 (en) * 1997-12-22 2001-01-02 Lifecor, Inc. Battery management apparatus for portable electronic devices
CN101158865A (en) * 2007-11-13 2008-04-09 中国移动通信集团福建有限公司 Electricity generator monitoring system device
CN102636147A (en) * 2012-03-31 2012-08-15 铁道第三勘察设计院集团有限公司 Deformation monitoring method for existing railway line
CN103115788A (en) * 2012-11-20 2013-05-22 上海理工大学 Indoor model experience device with existing tunnel affected by double subway construction
CN103196421A (en) * 2013-01-22 2013-07-10 中交天津港湾工程研究院有限公司 Automatic inspection type layered settlement instrument
CN103363954A (en) * 2013-07-22 2013-10-23 广西土木勘察检测治理有限公司 Land subsidence monitoring system

Similar Documents

Publication Publication Date Title
CN103913146B (en) The continuous operational monitoring station of GNSS
CN201811722U (en) Tunnel surrounding rock deformation monitoring and alarm device
CN202956104U (en) Electricity transmission line pole tower inclination monitoring system
CN202030825U (en) Deep well anode/cathode protection device for protecting embedded steel pipeline
CN204177381U (en) A kind of fiber bragg grating inclinometer device
CN104595728B (en) The warning monitoring system and its method of work of a kind of underground piping interface seepage
CN203949658U (en) The continuous operational monitoring of GNSS station
CN103412550A (en) Long-distance automation monitoring method of electric power tunnel pipe-jacking construction
CN104950921A (en) Safety monitoring system for building leveling
CN106647662A (en) Real-time online monitoring system for safety construction of urban excavation
CN201892527U (en) Pipe section joint opening monitoring device for electric power tunnels
CN216278017U (en) Intelligent monitoring and early warning equipment for large-area suspended-roof goaf
CN205103980U (en) Transmission line shaft tower slope analysis alarm device
CN203858731U (en) Beidou system-based transmission line geological disaster monitoring system
CN207195825U (en) A kind of buried oil-gas pipeline protection device in Sbusidence Damage area
CN105180896A (en) Sandy soil pipeline settlement monitoring method
CN204611354U (en) A kind of pipe network detection device
CN205079756U (en) Settlement monitoring device is prevented to sandy soil pipeline
CN208479835U (en) A kind of console mode internet of things equipment based on video camera
CN206684904U (en) A kind of Mine production monitoring device
CN203025912U (en) Anti-sloughing alarming system for high-danger side slope
CN102392256A (en) Wind/solar/electric complementary network anticorrosion system for buried steel pipelines
CN212112675U (en) Quick strutting arrangement of foundation ditch
CN102610934B (en) Construction method for reducing ground resistance of wind driven generator
KR20130016890A (en) On line monitoring system of underground utility

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20151223

RJ01 Rejection of invention patent application after publication